BIM coordination study

Pipe and beam in section

BeforePipe intersects beam
The orange pipe is inside the hatched concrete section.
AfterPipe clears beam
The pipe sits above the beam. A dimension line marks the gap.

17 cm clearance after raising the pipe by 60 cm.

Raise the pipe in the model
Scope and sources

The top of the beam is at 2.30 m in the model. The pipe centreline moves from 2.00 m to 2.60 m. With an outside radius of 13 cm, the underside of the raised pipe is at 2.47 m.

The clash check compares the axis-aligned bounding boxes of the two elements. This example excludes insulation and installation tolerances.

Element and geometry
A pipe with a 13 cm outside radius crosses a beam.
BIM workflow
In the coordination study I raise the pipe centreline by 60 cm and compare the two sections.
What I checked
The model gives 17 cm from the top of the beam to the underside of the pipe. The study excludes insulation and installation tolerances.
Evidence
Before and after sections taken from the same model geometry.