Hooman Ellyoun / Work

Existing building and connections

How does the extension connect to the existing building?

The new foundation slab connects to the existing structure at four points. Detail A shows the same section at each one.

My contribution

I coordinated the changes with the design team, then updated the model and drawings.

The structural consultant prepared the reinforcement drawing, including detail A.

Four circled connections in the foundation slab reinforcement plan, each referring to detail A. Detail A · reinforcement drawingOpen full drawing

Coordination elsewhere on this project

My coordination work on the roof storey

My role in the refurbishment

Updating the model and drawings

I agreed the drawing changes with the design team and incorporated them into the model and drawings. The reinforcement drawing shown here is the structural consultant’s.

The external consultant’s foundation slab reinforcement drawing shows the four slab projections and Detail A.Enlarge reinforcement drawing
Who worked on this?
Document
The structural consultant prepared the formwork and reinforcement drawings.
My role
I coordinated the connections with the team and incorporated the agreed changes into the model and drawings.
Prepared for the web
Numbers 1 to 4 show where detail A applies on the plan.
See my contribution

Stair and floor slab on the roof storey

Roof storey

In the roof storey, the reinforcement drawings for the stair and the slab between the steel beams were missing.

I requested the missing drawings and identified both elements in the request: the roof-storey stair and the slab between the steel beams.

My request concerned the roof storey. Detail A above belongs to the foundation slab.

Scope
Roof storey
Documents requested
Reinforcement for the stair and the slab between the steel beams
Summary of the documented drawing coordination

Formwork and reinforcement plans

The structural consultant’s drawings cover the foundation slab and ground floor. The four connections are marked on the slab reinforcement plan.

Open reinforcement drawing
Another work sample: compare two external drawing revisions
External formwork drawing with check marks for the foundation slab and ground floor.Enlarge formwork drawing
Who worked on this?
Document
The structural consultant prepared the formwork and reinforcement drawings.
My role
I coordinated the connections with the team and incorporated the agreed changes into the model and drawings.
Prepared for the web
Numbers 1 to 4 show where detail A applies on the plan.
See my contribution
For our conversation
View related experience in my CV
Scope and sources

The structural engineer produced the reinforcement drawing and detail A. I coordinated the documents and incorporated agreed changes in the model and drawings. The explanatory model locates the four connections.

Element and geometry
Four connections between the new foundation slab and the existing building.
BIM workflow
I coordinated changes with the design team and updated the model and drawings.
What I checked
I matched the four plan locations to the same detail A. My separate request for stair and slab drawings concerned the roof storey.
Evidence
Foundation plan and detail A from the structural consultant’s reinforcement drawing.