I compared the geometry in two drawing revisions issued by the structural engineer. Bar marks 6 and 103 show how the change was recorded in the bar schedule.
Bar schedule comparison
Original issue: bar mark 6, nine bars at 3.75 m each.Revision A: bar mark 6, four bars at 3.75 m each.New bar mark 103: five bars at 4.50 m each.
See the corresponding drawing detailsBottom reinforcement before the revisionBottom reinforcement in revision AScope and sources
I compared two reinforcement drawings issued by the structural engineer. The details and schedule rows refer to the same area before and after revision A. My work shown here is the geometric comparison; reinforcement design and approval are outside its scope.
Element and geometry
Bottom reinforcement in the same drawing area before and after revision A.
BIM workflow
I compared the structural engineer’s two revisions against the geometry and bar schedule.
What I checked
Bar mark 6 went from nine bars to four. Five bars appear under the new mark 103.
Evidence
Matching plan details and schedule rows. Reinforcement design and approval were outside my role.
Bauteil und Geometrie
Untere Bewehrung im gleichen Planausschnitt vor und nach Index A.
Arbeitsweise
Ich habe zwei Planstände des Tragwerksplaners anhand der Geometrie und der Stabliste verglichen.
Prüfung
Bei Position 6 sank die Stückzahl von neun auf vier. Fünf Stäbe erscheinen unter der neuen Position 103.
Beleg
Die zugehörigen Ausschnitte und Listenzeilen. Bewehrungsbemessung und Freigabe gehörten bei diesem Vergleich nicht zu meinen Aufgaben.
عضو و هندسه
آرماتور پایین در یک محدودهٔ ثابت از نقشه، پیش و پس از بازنگری A.
روش کار
دو نسخهٔ نقشهٔ مشاور سازه را از روی هندسه و جدول میلگرد مقایسه کردم.
کنترل انجامشده
تعداد میلگردهای شمارهٔ ۶ از نُه به چهار رسید. پنج میلگرد با شمارهٔ جدید ۱۰۳ در جدول آمد.
مدرک
جزئیات متناظر پلان و ردیفهای جدول میلگرد. طراحی و تأیید آرماتورها در حیطهٔ کار من نبود.